Fireline FP5W – Installed in Hale
DOWNLOAD FIRELINE BROCHUREThe gas was cut and capped by Trafford Gas. We cut and removed the tiles on the inset of the cast fire back. We removed all the brickwork in the chamber and installed a concrete lintel. The chimney stack was swept to ensure no obstructions before we installed a multi-fuel liner. Inside the chamber, we cement boarded it, this can be painted if the customer wants to in a matt emulsion. We then installed a concrete base as the customer wanted to supply their own tiles. Our tiler went in after us and laid the hearth. Once the hearth was installed and set we installed the Fireline FP5w multifuel stove. Perfect installation and transformation. Very happy customers!